July 12, 2024 |
Asphalt is complete and sod has been installed. The only remaining work is watering the sod.
Please be advised, this will serve as the final weekly update for the Borland Street Reconstruction project. Thank you for your patience and cooperation throughout the duration of this project.
Questions or Concerns can be directed to the Project Public Relations Person Doug Larocque from John Bravakis Enterprises Ltd. at 705-209-5860 or by email at douglarocque011@gmail.com.
|
July 5, 2024 |
Borland Street East and Borland Street West
West Street North/Borland Street Intersection
- Traffic controls will be set up on July 8 in order to mill asphalt on the south half, then traffic controls will be flipped to mill the north half. Following this, traffic controls will be removed overnight.
- Traffic controls will be set up again on July 10 in order to complete top lift asphalt on the south half, then traffic controls will be flipped to pave the north half. Following this, traffic controls will be removed.
|
June 28, 2024 |
Borland Street East from Peter Street North to West Street North
- Base asphalt, retaining wall and sidewalk are complete.
- Driveways will be complete this week
- Grading, topsoil and sod is scheduled to be completed next week
- Toplift asphalt is scheduled for July 9
- This section is Closed to Local Traffic Only, with no Access Restrictions
Borland St West from West Street North to Lawrence Avenue
- Base asphalt and sidewalk are completed
- Driveways will be complete this week and if needed next Tuesday
- Grading, topsoil and sod is scheduled to be completed next week
- Toplift asphalt is scheduled for July 9
- This section is Closed to Local Traffic Only, with no Access Restrictions
|
June 21, 2024 |
Borland Street East from Peter Street North to West Street North
Work completed this week:
Borland Street West from West Street North to Lawrence Avenue
Work completed this week:
|
June 14, 2024 |
Borland Street East from Peter Street North to West Street North
Work completed this week:
Borland Street West from West Street North to Lawrence Avenue
Work completed this week:
-
All watermain has been installed and tested. Samples were collected on Thursday, June 13, and pending pass results, the proposed watermain and new water services will be connected to the existing services next week.
-
Road base construction is ongoing.
- Curbs will be poured next Tuesday/Wednesday and base asphalt is anticipated to be completed by June 26, 2024.
- Lawrence Avenue is currently closed and will remain closed until asphalt is complete. Borland Street West and Dalton Crescent are only accessible from West Street North.
|
June 7, 2024 |
Borland Street East from Peter Street North to West Street North
Work completed this week:
Borland Street West from West Street North to Lawrence Avenue
Work completed this week:
-
Sewer and watermain are anticipated to be completed by Friday, June 7.
-
Lawrence Avenue was closed on Thursday, June 6, and will remain closed until the end of next week. Borland Street West and Dalton Crescent are only accessible from West Street North until the end of next week.
Work to be completed next week:
|
May 31, 2024 |
Borland Street East from Peter Street North to West Street North
Work completed this week:
- The new watermain was connected to the existing watermain at both ends and existing services on May 29, 2024.
- Continuing general cleanup/restoration of this work zone.
- Borland Street East will remain accessible from both ends.
Borland Street West from West Street North to Lawrence Avenue
Work completed this week:
Work to be completed next week:
- Sanitary sewer, watermain and road base is scheduled to be constructed up to Lawrence Avenue.
|
May 24, 2024 |
Borland Street East from Peter Street North to West Street North
Work completed this week:
-
The watermain has been flushed and disinfected. Pending past results of water samples, the new watermain will be connected to the existing watermain at both ends and the existing services by Tuesday, May 28, 2024.
-
Continuing general cleanup/restoration of this work zone.
- Borland Street East will remain accessible from both ends.
Borland Street West from West Street North to Lawrence Avenue
Work completed this week:
-
Sanitary sewer, watermain and road base will be completed through the eastern side of Dalton Crescent by Friday, May 24, 2024.
- By the end of day on Friday, May 24, 2024, both sides of Dalton Crescent will be open and Borland Street West will be closed at 32/36 Borland Street West. Houses west of this point are accessible from Lawrence Avenue and houses east of this point will be accessible from West Street North.
Work to be completed next week:
- Sanitary sewer, watermain and road base will be constructed through the intersection of the western side of Dalton Crescent. Note: During this work, the western side of Dalton Crescent will be closed and Dalton Crescent North and South will only be accessible from West Street North via the eastern side of the Dalton Crescent intersection.
|
May 17, 2024 |
Borland Street East from Peter Street North to West Street North
Work completed this week:
Work to be completed next week:
Borland Street West from West Street North to Lawrence Avenue
Work completed this week:
- Sanitary sewer and road base is anticipated to be completed from West Street North up to the eastern side of Dalton Crescent by Friday, May 17, 2024.
- By end of day on Friday, May 17, 2024, all driveways between West Street North and the eastern side of Dalton Crescent will only be accessible from West Street North. The remainder of driveways past this point will be accessible from Lawrence Avenue.
Work to be completed next week:
- Watermain installation from West Street North to 20m west of the eastern side of Dalton Crescent.
-
Sanitary sewer and road base will be constructed through the intersection of Borland Street West and the eastern side of Dalton Crescent. Note: During this work, the eastern side of Dalton Crescent will be closed and Dalton Crescent North and South will only be accessible via the eastern side of the Dalton Crescent intersection.
|
May 10, 2024 |
Borland Street East from Peter Street North to West Street North
Work completed this week:
- Road base, watermain, sanitary and storm sewer in this area.
- Curb is expected to be completed Friday, May 10, 2024.
- Borland Street East is currently accessible from both ends.
Work to be completed next week:
- New watermain will be commissioned/tested, and pending past results, will be connected to the existing watermain at both ends and to existing services.
- Base asphalt is scheduled for Tuesday, May 14, 2024.
- General cleanup of this work zone.
- On Monday, May 13, 2024, and Tuesday, May 14, 2024, this work area will only be accessible from Peter Street North.
Borland Street West from West Street North to Lawrence Avenue
Work completed this week:
- Temporary water supply has been successfully commissioned and connected to the existing watermain and existing services.
Work to be completed next week:
- Connection to the existing sanitary sewer at the intersection of West Street North is scheduled to be completed on Monday, May 13, 2024, and Tuesday, May 14, 2024. Note: During the connection, West Street North will be reduced to one lane and traffic will be controlled with temporary traffic lights as per the Traffic Control Plan. Borland Street West and Dalton Crescent will only be accessible from Lawrence Avenue. A Notice to Residents advising of the lane restrictions was hand delivered to residents by JBE on Friday, May 10, 2024.
- Road base, watermain and sanitary sewer installation will start in this area on Monday, May 13, 2024.
|
May 3, 2024 |
Borland Street East
Road base, watermain, sanitary and storm sewer is anticipated to be completed past 9 Borland Street East by Friday, May 3, 2024. The installation of servicing and road granulars, including curbs, is estimated to be completed next week.
Please note that driveways on Borland Street East from West Street North to Peter Street North and driveways on Borland Street West from West Street North to Dalton Crescent South are accessible from the West Street North and Peter Street North intersections.
Borland Street West
Surface removals have been completed. Temporary water supply has been installed, tested, and samples have been sent to the lab for testing. Pending these test results, temporary connections to homes are expected to be completed next week.
|
April 26, 2024 |
Borland Street East from Peter Street North to West Street North and Borland Street West from West Street North to Lawrence Avenue were closed on Monday, April 25, 2024. Residents and emergency services will have access to Borland Street East via West Street North. Please follow the detour signage (D-1, D-2, D-3, D-4).
All surface removals (asphalt driveway, sidewalk, curbs, etc.) are estimated to be completed by Friday, April 26, 2024. Installation of a temporary water supply on Borland Street West is estimated to be ready for testing/commissioning by April 30, 2024. Pipe installation and roadwork up to Granular B is currently estimated to be completed by Friday, May 2, 2024.
|
|