Project Summary |
Location: Jarvis Street from West Street North to Bay Street |
Budget: $7,000,000 |
Timeline: Construction on the first phase from Laclie Street to Bay Street is commencing in May, 2025. Construction on the second phase from West Street North to Laclie Street is anticipated to occur in 2026, subject to Council approval. |
Consultant: Pinestone Engineering Limited Contractor: Phase 1 - North Rock Group |
Project Contact: John Rae, Project Manager, City of Orillia Sarah Anema, Public Relations Officer, North Rock Group - sarah@northrockgroup.com or 647-389-1700 |
Project Description |
The project is the reconstruction of Jarvis Street from Laclie Street to Bay Street into a two-lane standard roadway with additional layby parking areas between Canice Street and Bay Street. This includes the replacement of underground infrastructure, such as watermains, sanitary sewers, storm sewers, as well as reconstruction of the road surface and sidewalks. The project also includes replacement of the existing watermain, which runs through Couchiching Beach Park to Lightfoot Drive. |
Project Documentation |
Road Closures and Transit Route Modifications |
May 7th- Please be aware there will be a hard road closure on Jarvis Street east of Laclie Street. Until further notice there will be no through traffic on Jarvis Street between Laclie Street and Parkview Avenue. Access to all residents between Laclie Street and Parkview Avenue will be from Parkview Avenue.
Detour signage will be in place. Two transit stops will be out of service and temporary stops are located on Borland Street East and Bay Street. |
Project Updates - Phase 1 |
To receive biweekly updates directly, sign up for the mailing list below.