Contact(s)
Project Summary |
Location: Orillia Water System Master Plan Update |
Budget: $175,000 |
Timeline: Master Plan anticipated to be completed by July 2022. |
Current Status: Draft received for internal review. |
Consultant: Tatham Engineering Limited |
Project Contacts: Suzanne Troxler, 705-444-2565, stroxler@tathameng.com Stephen Gendron, 705-325-2212, sgendron@orillia.ca |
The City of Orillia has retained the services of the Tatham Engineering Limited to undertake an Update to the City’s Water Master System Master Plan (2015).
The main objectives of the project are to:
- Develop a comprehensive inventory of the existing water system in the City of Orillia.
- Update population and water demand forecasting that will allow the City of Orillia to plan the expansion and improvement of the City of Orillia’s water system for a period of thirty (30) years.
- Update a practical prioritized capital plan for the thirty-year planning forecast for the water system.
- Complete a Water System Master Plan in conformity with the latest version of the Municipal Class Environmental Assessment (MCEA) process, and completed in accordance with Approach 2 in the MCEA guideline, which is a level of investigation, consultation and documentation sufficient to fulfil the requirements of Schedule B projects, and provide the basis for specific Schedule C projects identified.
Project Documentation |
Public Information Centre |
Map of the Study Area